Project

EXTENSION OF THE SOUTHERN LINE OF THE LIGHT METRO

Description of the work

EXTENSION OF THE SOUTHERN LINE OF THE LIGHT METRO

This involves the creation of a new section of the public transport network in the El Mourouj region. Carried out in collaboration with Alstom, this infrastructure project aims to improve urban mobility by providing a fast and efficient transport link.

DÉTAILS DU PROJET

Client: TRANSTU

Fin du projet: 2008

Localisation: El Mourouj, Ben Arous

Montant: 14 600 000 DT

Etendue des travaux:

  • Earthworks and preparation of the right-of-way for the line
  • Construction work on the railway platform
  • Installation work for 6,700 linear meters of double track for the metro
  • Construction work on eleven passenger stations, each 75 to 80 meters long.
  • Construction work on a bus-metro interchange hub
  • Construction work on a bus parking lot and a car park
  • Construction work on the annex buildings
  • Installation of RI60 grooved rails on wooden sleepers
  • Work to install ballast under the sleepers
  • Work to encase the track in a layer of unreinforced concrete vibrated along its entire height

Let's build the future project by project

Projects

Olympic Stadium

The largest stadium in Tunisia, with a capacity of 60,000; SBF constructed the entire load-bearing structure of the stadium, consisting of 64 portals, each 33 meters high.

Tunisian-Libyan Bank

SBF carried out the construction of the office building for the headquarters of the Tunisian-Libyan Bank BTL.

National Museum

The present project is located on the grounds of the Bardo National Museum, and mainly comprises two construction sites that were carried out in parallel and which are

Amen Clinic

This project consists of a basement, ground floor and 6 floors, it was completed on schedule and in accordance with the client’s objectives.

Transit Village

Construction of a village of Arab-Muslim architecture on a total area of ​​11,500 m2, of which 9,500 m2 are covered areas.

Azur City

An ambitious architectural project: On the banks of the suburbs, the SBF team carried out the structural work for the main commercial and leisure center in Tunisia.

Tunis City

SBF, the successful bidder for the “Structures” package of the project (with a 10-month deadline), proposed and implemented, as a replacement for the traditional solution

phosphoric acid unit

The M’dhila2 project involves a new 54% concentrated phosphoric acid production plant, with the aim of producing triple superphosphate at the existing M’dhila1 plant.