Société Bouzguenda Frères

Project

Construction of a Shipping Cruise Transit Village

Description of the work

Construction of a Shipping Cruise Transit Village

The project involves the construction of a residential complex in the Arab-Muslim architectural style. The development comprises fifteen separate blocks and two terminals. It aims to create a welcoming and serviced space for cruise passengers and other visitors, offering an aesthetically pleasing environment inspired by local architecture.

DÉTAILS DU PROJET

Client: Shipping Cruise

Fin du projet: 2009

Localisation: La Goulette, Tunis

Montant: 6 600 000 DT

Etendue des travaux:

  • Earthworks
  • Foundation work for all blocks and terminals.
  • Construction work on the reinforced concrete structure
  • Masonry work for the construction of walls and partitions.
  • Exterior and interior plastering application work.
  • waterproofing work
  • Installation work for marble and stone cladding.
  • Works for the execution of external developments (VRD).

Chiffres clés:

  • Area: 11,500 m²
  • Covered area: 9,500 m²
  • Concrete: 6,000 m³
  • Concrete steel: 600 tonnes

Let's build the future project by project

Projects

Olympic Stadium

The largest stadium in Tunisia, with a capacity of 60,000; SBF constructed the entire load-bearing structure of the stadium, consisting of 64 portals, each 33 meters high.

Tunisian-Libyan Bank

SBF carried out the construction of the office building for the headquarters of the Tunisian-Libyan Bank BTL.

National Museum

The present project is located on the grounds of the Bardo National Museum, and mainly comprises two construction sites that were carried out in parallel and which are

Amen Clinic

This project consists of a basement, ground floor and 6 floors, it was completed on schedule and in accordance with the client’s objectives.

Transit Village

Construction of a village of Arab-Muslim architecture on a total area of ​​11,500 m2, of which 9,500 m2 are covered areas.

Azur City

An ambitious architectural project: On the banks of the suburbs, the SBF team carried out the structural work for the main commercial and leisure center in Tunisia.

Tunis City

SBF, the successful bidder for the “Structures” package of the project (with a 10-month deadline), proposed and implemented, as a replacement for the traditional solution

phosphoric acid unit

The M’dhila2 project involves a new 54% concentrated phosphoric acid production plant, with the aim of producing triple superphosphate at the existing M’dhila1 plant.