EXTENSION OF THE BAXTER FACTORY

Description of the work

EXTENSION OF THE BAXTER FACTORY

The project involves the expansion of the Baxter Bieffe Medical Manufacturing plant in Tunisia, located in Oued Ellil (Manouba Governorate) and owned by the American group Baxter International Inc., which specializes in the manufacture of medical products. This project aims to increase the production capacity of the existing Baxter plant dedicated to the manufacture of medical and pharmaceutical products.

DÉTAILS DU PROJET

Client: BAXTER Bieffe Medital Manufacturing

Fin du projet: 2024

Localisation: OUED ELLIL, MANOUBA

Montant: 10 500 000 DT

Etendue des travaux:

  • Area: 5,000 m²
  • The work to extend the BAXTER plant includes:
  • Reinforced concrete structure
  • Reinforcement of the existing metal structure
  • Metal framework
  • Masonry, brickwork and plastering
  • Coatings
  • Waterproofing and Insulation
  • Miscellaneous works

Let's build the future project by project

Projects

Olympic Stadium

The largest stadium in Tunisia, with a capacity of 60,000; SBF constructed the entire load-bearing structure of the stadium, consisting of 64 portals, each 33 meters high.

Tunisian-Libyan Bank

SBF carried out the construction of the office building for the headquarters of the Tunisian-Libyan Bank BTL.

National Museum

The present project is located on the grounds of the Bardo National Museum, and mainly comprises two construction sites that were carried out in parallel and which are

Amen Clinic

This project consists of a basement, ground floor and 6 floors, it was completed on schedule and in accordance with the client’s objectives.

Transit Village

Construction of a village of Arab-Muslim architecture on a total area of ​​11,500 m2, of which 9,500 m2 are covered areas.

Azur City

An ambitious architectural project: On the banks of the suburbs, the SBF team carried out the structural work for the main commercial and leisure center in Tunisia.

Tunis City

SBF, the successful bidder for the “Structures” package of the project (with a 10-month deadline), proposed and implemented, as a replacement for the traditional solution

phosphoric acid unit

The M’dhila2 project involves a new 54% concentrated phosphoric acid production plant, with the aim of producing triple superphosphate at the existing M’dhila1 plant.