Description of the work

KORBA GAS PUMPING STATION

The project consists of the construction of a set of facilities essential to the transport and compression of gas in order to strengthen the gas infrastructure of the Korba region by setting up a high-performance pumping station that complies with international standards.

DÉTAILS DU PROJET

Client: Scogat, Snamprogetti, SAIPEM

Fin du projet: 2007

Localisation: Korba, Nabeul

Montant: 15 400 000 DT

Etendue des travaux:

  • Earthworks
  • Construction work for foundations and reinforced concrete structures for the three turbochargers and the various buildings
  • Construction work on the cabins for the turbochargers using metal framing.
  • Construction work on the control room, the workshop/store, the boiler building, the guard post, the electrical cabin, the CO2 battery and the canteen.
  • Construction work for underground networks, including pipes, wastewater drainage systems and conduits for cables.
  • Construction work on tanks and filters.
  • Exterior development work, including roads, lighting and site fencing.

Chiffres clés:

  • Earthworks: 50,000 m³
  • Reinforced concrete: 15,000 m³
  • Metal framework: 400 tonnes
  • Outdoor facilities: 17 hectares

Let's build the future project by project

Projects

Olympic Stadium

The largest stadium in Tunisia, with a capacity of 60,000; SBF constructed the entire load-bearing structure of the stadium, consisting of 64 portals, each 33 meters high.

Tunisian-Libyan Bank

SBF carried out the construction of the office building for the headquarters of the Tunisian-Libyan Bank BTL.

National Museum

The present project is located on the grounds of the Bardo National Museum, and mainly comprises two construction sites that were carried out in parallel and which are

Amen Clinic

This project consists of a basement, ground floor and 6 floors, it was completed on schedule and in accordance with the client’s objectives.

Transit Village

Construction of a village of Arab-Muslim architecture on a total area of ​​11,500 m2, of which 9,500 m2 are covered areas.

Azur City

An ambitious architectural project: On the banks of the suburbs, the SBF team carried out the structural work for the main commercial and leisure center in Tunisia.

Tunis City

SBF, the successful bidder for the “Structures” package of the project (with a 10-month deadline), proposed and implemented, as a replacement for the traditional solution

phosphoric acid unit

The M’dhila2 project involves a new 54% concentrated phosphoric acid production plant, with the aim of producing triple superphosphate at the existing M’dhila1 plant.