Description of the work

Renovation of Passenger Stations on the TGM Line – Lot 2

This project involved the complete renovation of the eight passenger stations on the Tunis-Goulette-Marsa (TGM) railway line with the aim of modernizing public transport infrastructure, improving the passenger experience and ensuring the safety and functionality of the facilities.

DÉTAILS DU PROJET

Client: TUNIS TRANSPORT COMPANY - TRANSTU

Fin du projet: 2020

Localisation: La goulette, Le Kram, Carthage

Montant: 7 000 000 DT

Etendue des travaux:

  • Demolition and reconstruction work on the platforms, ticket offices and technical facilities
  • Total or partial reconstruction of fences
  • Restoration of floor coverings and platform improvements.
  • Exterior landscaping around the stations
  • Metal framework construction
  • Painting and signage work
  • Electrical work
  • Sanitary plumbing work

Spécificités du projet:

  • Stations located in popular and busy urban areas require work management that minimizes the impact on users.
  • Work carried out in the presence of passengers and with a train in service, requiring strict safety measures and meticulous site organization.
  • Location of stations in an archaeological zone, involving close coordination and compliance with the guidelines of the National Heritage Institute (INP).
  • Complex works carried out in narrow areas and near dilapidated buildings, requiring careful management of the many underground and overhead utility networks present on the site.

Let's build the future project by project

Projects

Olympic Stadium

The largest stadium in Tunisia, with a capacity of 60,000; SBF constructed the entire load-bearing structure of the stadium, consisting of 64 portals, each 33 meters high.

Tunisian-Libyan Bank

SBF carried out the construction of the office building for the headquarters of the Tunisian-Libyan Bank BTL.

National Museum

The present project is located on the grounds of the Bardo National Museum, and mainly comprises two construction sites that were carried out in parallel and which are

Amen Clinic

This project consists of a basement, ground floor and 6 floors, it was completed on schedule and in accordance with the client’s objectives.

Transit Village

Construction of a village of Arab-Muslim architecture on a total area of ​​11,500 m2, of which 9,500 m2 are covered areas.

Azur City

An ambitious architectural project: On the banks of the suburbs, the SBF team carried out the structural work for the main commercial and leisure center in Tunisia.

Tunis City

SBF, the successful bidder for the “Structures” package of the project (with a 10-month deadline), proposed and implemented, as a replacement for the traditional solution

phosphoric acid unit

The M’dhila2 project involves a new 54% concentrated phosphoric acid production plant, with the aim of producing triple superphosphate at the existing M’dhila1 plant.